Archive

ShareThis Page
Allegheny County controller’s audit cites Tarentum project among cost overrun concerns | TribLIVE.com
Valley News Dispatch

Allegheny County controller’s audit cites Tarentum project among cost overrun concerns

487877vndbridgeoverrundk112918
Brian C. Rittmeyer
Allegheny County Controller Chelsa Wagner said a nearly $500,000 overrun for a wall that was part of a channel restoration project on Bull Creek in Tarentum contributed to $6 million in extra costs across a dozen county poblic works projects audited.

A nearly $500,000 cost overrun on a project to restore a Tarentum creek channel contributed to $6 million in additional costs across a dozen projects in Allegheny County, county Controller Chelsa Wagner said.

The extra costs more than consumed the revenue raised from a new $5 vehicle registration fee Allegheny County residents pay to fund road and bridge work, a 27-page report released by Wagner says.

Wagner said the county must tighten standards for firms designing and carrying out public works projects to prevent construction cost overruns.

Overruns on the dozen projects examined averaged almost double the 10 percent that would typically cover change orders and is considered the industry standard, Wagner said.

“Cost overruns resulting from omitting necessary tasks from design plans and bids not only sap county resources that could go to other projects, they open the door to unscrupulous practices such as ‘bid rigging,’ which drive costs up even further,” Wagner said.

“When cost overruns become commonplace, contractors may see the opportunity to secure contracts by bidding below their actual anticipated cost,” she said. “This is why close oversight of design work to prevent the necessity of excessive change orders is essential.”

According to Wagner’s report, the Bull Creek channel restoration project near the Tarentum Bridge originally included installing a gabion wall on the creek’s eastern bank between a railroad bridge and the Fourth Avenue bridge.

While the contractor was excavating for the wall’s installation, “it was determined that the pier depth of the Tarentum Bridge was too shallow to continue. The excavation was shut down by PennDOT to prevent any further instability to the Tarentum Bridge.”

The project designer had to develop an adjacent caisson wall to replace the original wall and avoid more excavation surrounding the Tarentum Bridge pier.

The change added about $488,000 to the project’s roughly $1 million original cost.

Wagner’s audit recommended building limits on added costs due to design omissions into engineering contracts, and conducting thorough internal reviews of design specifications to ensure they are complete before issuing requests for construction bids.

Firms that repeatedly submit incomplete designs should be restricted from county engineering work, she said.

In responding to the audit, public works Director Stephen Shanley said 33 projects were completed from 2015 through 2017. The bids for those projects was $81.1 million and the final contract amount was $81.3 million. That’s a $202,525 difference and a change in costs of 0.25 percent — well below the 10 percent industry standard.

“Our project managers that oversee the design and construction strive to limit project issues and when they arise handle them as effectively as possible,” Shanley said in a written response. “This can be seen through the bid costs and final construction costs of the projects bid through 2015-2017 that have been completed. It is our opinion that this is a more accurate representation of the projects designed and constructed by this department than those selected for this audit.”

The $5 surcharge on vehicle registrations in Allegheny County took effect in 2016. It raised $4.8 million in 2017, which is $1.2 million less than the cost overruns on the projects that auditors examined.

“When every Allegheny County driver saw their vehicle registration fee rise by $5 two years ago, they expected that to result in safer roads and bridges,” Wagner said. “But we have seen cost overruns that could well have been prevented through due diligence by the county to burn through this amount and more.

“Greater safeguards simply must be put in place to ensure that every dollar available for investment in this vital priority is spent wisely.”

Brian Rittmeyer is a Tribune-Review staff writer. You can contact Brian at 724-226-4701, [email protected] or via Twitter @BCRittmeyer.

TribLIVE commenting policy

You are solely responsible for your comments and by using TribLive.com you agree to our Terms of Service.

We moderate comments. Our goal is to provide substantive commentary for a general readership. By screening submissions, we provide a space where readers can share intelligent and informed commentary that enhances the quality of our news and information.

While most comments will be posted if they are on-topic and not abusive, moderating decisions are subjective. We will make them as carefully and consistently as we can. Because of the volume of reader comments, we cannot review individual moderation decisions with readers.

We value thoughtful comments representing a range of views that make their point quickly and politely. We make an effort to protect discussions from repeated comments either by the same reader or different readers

We follow the same standards for taste as the daily newspaper. A few things we won't tolerate: personal attacks, obscenity, vulgarity, profanity (including expletives and letters followed by dashes), commercial promotion, impersonations, incoherence, proselytizing and SHOUTING. Don't include URLs to Web sites.

We do not edit comments. They are either approved or deleted. We reserve the right to edit a comment that is quoted or excerpted in an article. In this case, we may fix spelling and punctuation.

We welcome strong opinions and criticism of our work, but we don't want comments to become bogged down with discussions of our policies and we will moderate accordingly.

We appreciate it when readers and people quoted in articles or blog posts point out errors of fact or emphasis and will investigate all assertions. But these suggestions should be sent via e-mail. To avoid distracting other readers, we won't publish comments that suggest a correction. Instead, corrections will be made in a blog post or in an article.