Arnold Palmer Regional Airport gets new terminal exit, plans work on new access road

Jeff Himler
gtrWestairport101117
Jeff Himler | Tribune-Review
Doors are to be installed in the background area covered by boards, to create a new exit vestibule in the baggage claim section of the terminal at Arnold Palmer Regional Airport in Unity.

Work to add a new terminal exit at Arnold Palmer Regional Airport is wrapping up, and officials expect to soon begin construction of a new access road off Route 981.

Engineer Scott Kunselman of GAI Consultants told the Westmoreland County Airport Authority on Tuesday that glass doors for the new exit vestibule at the Unity facility are to be installed this week and the project should be finished by the end of the month.

The new exit will allow passengers on arriving flights to walk from the terminal’s baggage claim area directly to the parking lot without encountering people entering the building to board flights, rent cars or patronize DeNunzio’s restaurant, authority Executive Director Gabe Monzo said.

The doors and a vestibule are replacing a large window.

Airport staff completed related improvements in the terminal.

“Our guys did all the remodeling you see in the terminal, new lighting and new carpeting,” board member Don Rossi said.

The authority approved a subcontractor for the vestibule, Glass Erectors. Kunselman said its fee of $18,895 is included in a $35,400 general construction contract already awarded to Swede Construction. Swede also will be paid $12,445 for electrical work associated with the project. Whitby Inc. is handling heating, ventilation and air conditioning at a cost of $15,600.

Subcontractor Parking Lot Paving Co., with a fee of $11,961.22, was approved to assist general contractor A. Liberoni Inc. with the new airport access road. The road will be located northeast of the existing main entrance and will connect to a recently completed roundabout on Route 981 that also provides access to Charles Houck and Gravel Hill roads.

Kunselman said grooving of pavement and placement of permanent markings are to be completed in October to close out Derry Construction’s resurfacing of the Arnold Palmer runway. Axtell’s Inc. was approved as a subcontractor, with its fee of $141,574 included in the $2.5 million project cost.

The runway was shut down Sept. 12-20 for the project.

“It looks really nice,” Monzo said of the new pavement. “This was a total effort of everybody at this airport, with the nine-day shutdown of the operation and the things they improved in the terminal.”

Jeff Himler is a Tribune-Review staff writer. Reach him at 724-836-6622, [email protected] or via Twitter @jhimler_news.

TribLIVE commenting policy

You are solely responsible for your comments and by using TribLive.com you agree to our Terms of Service.

We moderate comments. Our goal is to provide substantive commentary for a general readership. By screening submissions, we provide a space where readers can share intelligent and informed commentary that enhances the quality of our news and information.

While most comments will be posted if they are on-topic and not abusive, moderating decisions are subjective. We will make them as carefully and consistently as we can. Because of the volume of reader comments, we cannot review individual moderation decisions with readers.

We value thoughtful comments representing a range of views that make their point quickly and politely. We make an effort to protect discussions from repeated comments either by the same reader or different readers

We follow the same standards for taste as the daily newspaper. A few things we won't tolerate: personal attacks, obscenity, vulgarity, profanity (including expletives and letters followed by dashes), commercial promotion, impersonations, incoherence, proselytizing and SHOUTING. Don't include URLs to Web sites.

We do not edit comments. They are either approved or deleted. We reserve the right to edit a comment that is quoted or excerpted in an article. In this case, we may fix spelling and punctuation.

We welcome strong opinions and criticism of our work, but we don't want comments to become bogged down with discussions of our policies and we will moderate accordingly.

We appreciate it when readers and people quoted in articles or blog posts point out errors of fact or emphasis and will investigate all assertions. But these suggestions should be sent via e-mail. To avoid distracting other readers, we won't publish comments that suggest a correction. Instead, corrections will be made in a blog post or in an article.