LOS ANGELES — The largest solar power plant of its type in the world — once promoted as a turning point in green energy — isn’t producing nearly as much energy as anticipated.

One of the reasons is as basic as it gets: The sun isn’t shining as much as expected.

Sprawling across about 5 square miles of federal desert near the California-Nevada border, the Ivanpah Solar Electric Generating System opened in February, with operators saying it would produce enough electricity to power a city of 140,000 homes.

So far, however, the complex is producing about half its expected annual output for 2014, according to calculations by the California Energy Commission.

It had been projected to produce its full capacity for 8 hours a day, on average.

“Factors such as clouds, jet contrails and weather have had a greater impact on the plant than the owners anticipated,” the agency wrote in a statement.

“During startup we have experienced … equipment challenges, typical with any new technology, combined with irregular weather patterns,” NRG spokesman Jeff Holland wrote in a statement. “We are confident that Ivanpah’s long-term generation projections will meet expectations.”

BrightSource Energy, which co-owns the plant with NRG Energy Inc. and Google Inc., said on its website that the weather has generally been substantially worse than historical averages — in other words, cloudy — resulting in reduced output in certain months.

It could take until 2018 for the plant backed by $1.6 billion in federal loan guarantees to hit its annual peak target, said NRG Energy.

The technology used at Ivanpah is different than the photovoltaic panels commonly used for rooftop solar installations. The plant’s solar-thermal system — sometimes called concentrated-solar thermal — relies on nearly 350,000 computer-controlled mirrors at the site, each the size of a garage door.

The mirrors reflect sunlight to boilers atop 459-foot towers — taller than the Statue of Liberty. The resulting steam drives turbines to produce electricity.

When the $2.2 billion complex opened, Energy Department Secretary Ernest Moniz called it a “symbol of the exciting progress” in renewable energy.

The agency says the project remains in good standing, but Kaitlin Meese, an analyst at research firm Bentek Energy, said its early production figures “do not paint a strong picture for solar-thermal technology development.”

The operation of such plants is highly dependent on weather conditions, and predicting when and how strongly the sun will shine is not a perfect science.

A little bit of inefficiency with mirrors can translate into a loss of power output ranging from small to significant, according to Neil Fromer, executive director of the Resnick Sustainability Institute at the California Institute of Technology.

Problems could include getting the thousands of mirrors pointed in exactly the right direction, especially in the cool early morning, or keeping them clean in the dusty Mojave Desert.

Operators initially expected to need steam from gas-powered boilers for an hour a day during startup. Once operations began, however, they found they needed to keep boilers running an average of 4 12 hours a day.

State energy regulators in August approved the plant’s request to increase the natural gas it is allowed to burn by 60 percent. More natural gas could be needed to operate boilers when clouds thicken, or to maintain output at the end of the day and extend the capability for power production, the company said.

“Because the plant requires sunlight to heat water and turn it to steam, anything that reduces the sunlight will affect steam conditions, which could damage equipment and potentially cause unsafe conditions,” said the state energy commission, which approved the request for increased gas use.


TribLIVE commenting policy

You are solely responsible for your comments and by using TribLive.com you agree to our Terms of Service.

We moderate comments. Our goal is to provide substantive commentary for a general readership. By screening submissions, we provide a space where readers can share intelligent and informed commentary that enhances the quality of our news and information.

While most comments will be posted if they are on-topic and not abusive, moderating decisions are subjective. We will make them as carefully and consistently as we can. Because of the volume of reader comments, we cannot review individual moderation decisions with readers.

We value thoughtful comments representing a range of views that make their point quickly and politely. We make an effort to protect discussions from repeated comments either by the same reader or different readers

We follow the same standards for taste as the daily newspaper. A few things we won't tolerate: personal attacks, obscenity, vulgarity, profanity (including expletives and letters followed by dashes), commercial promotion, impersonations, incoherence, proselytizing and SHOUTING. Don't include URLs to Web sites.

We do not edit comments. They are either approved or deleted. We reserve the right to edit a comment that is quoted or excerpted in an article. In this case, we may fix spelling and punctuation.

We welcome strong opinions and criticism of our work, but we don't want comments to become bogged down with discussions of our policies and we will moderate accordingly.

We appreciate it when readers and people quoted in articles or blog posts point out errors of fact or emphasis and will investigate all assertions. But these suggestions should be sent via e-mail. To avoid distracting other readers, we won't publish comments that suggest a correction. Instead, corrections will be made in a blog post or in an article.