Archive

Crack in beam shuts down San Francisco’s new $2B terminal | TribLIVE.com
U.S./World

Crack in beam shuts down San Francisco’s new $2B terminal

The Associated Press
2730022730027b2a313eb2c04cf59283ce2092e517c4
Commuters wait in lines for buses at the Temporary Transbay Terminal after the Salesforce Transit Center was closed Tuesday, Sept. 25, 2018, in San Francisco. San Francisco officials shut down the city’s celebrated new $2.2 billion transit terminal Tuesday after discovering a crack in a support beam under the center’s public roof garden. Coined the “Grand Central of the West,” the Salesforce Transit Center opened in August near the heart of downtown after nearly a decade of construction. It was expected to accommodate 100,000 passengers each weekday, and up to 45 million people a year.Eric Risberg | AP
273002273002ecb0ef62c195428484d23444cb51625e
The Salesforce Transit Center complex, stretching several blocks, is seen following its closure Tuesday, Sept. 25, 2018, in San Francisco. San Francisco officials shut down the city’s celebrated new $2.2 billion transit terminal Tuesday after discovering a crack in a support beam under the center’s public roof garden. Coined the “Grand Central of the West,” the Salesforce Transit Center opened in August near the heart of downtown after nearly a decade of construction. It was expected to accommodate 100,000 passengers each weekday, and up to 45 million people a year.Eric Risberg | AP
2730022730026e2e3b8e9afe430997924a7887526c01
People are directed around the Salesforce Transit Center following its closure Tuesday, Sept. 25, 2018, in San Francisco. San Francisco officials shut down the city’s celebrated new $2.2 billion transit terminal Tuesday after discovering a crack in a support beam under the center’s public roof garden. Coined the “Grand Central of the West,” the Salesforce Transit Center opened in August near the heart of downtown after nearly a decade of construction. It was expected to accommodate 100,000 passengers each weekday, and up to 45 million people a year.Eric Risberg | AP
273002273002bae65ef64b7340558f65bac62f92dc9d
San Francisco Police officers stand watch in the lower level of the Salesforce Transit Center following its closure Tuesday, Sept. 25, 2018, in San Francisco. San Francisco officials shut down the city’s celebrated new $2.2 billion transit terminal Tuesday after discovering a crack in a support beam under the center’s public roof garden. Coined the “Grand Central of the West,” the Salesforce Transit Center opened in August near the heart of downtown after nearly a decade of construction. It was expected to accommodate 100,000 passengers each weekday, and up to 45 million people a year.Eric Risberg | AP
27300227300247633ff024bd46c6bc3e1047759fd960
The lower level of the Salesforce Transit Center remains empty except for police, following its closure Tuesday, Sept. 25, 2018, in San Francisco. San Francisco officials shut down the city’s celebrated new $2.2 billion transit terminal Tuesday after discovering a crack in a support beam under the center’s public roof garden. Coined the “Grand Central of the West,” the Salesforce Transit Center opened in August near the heart of downtown after nearly a decade of construction. It was expected to accommodate 100,000 passengers each weekday, and up to 45 million people a year.Eric Risberg | AP
27300227300243bec2abf3fa4d279dfb63171949cf29
Mike Eshleman, with AC Transit, directs people away from the Salesforce Transit Center following its closure, Tuesday, Sept. 25, 2018, in San Francisco. San Francisco officials shut down the city’s celebrated new $2.2 billion transit terminal Tuesday after discovering a crack in a support beam under the center’s public roof garden. Coined the “Grand Central of the West,” the Salesforce Transit Center opened in August near the heart of downtown after nearly a decade of construction. It was expected to accommodate 100,000 passengers each weekday, and up to 45 million people a year.Eric Risberg | AP

SAN FRANCISCO — San Francisco officials shut down the city’s celebrated new $2.2 billion transit terminal Tuesday after discovering a crack in a support beam under the center’s public roof garden.

Coined the “Grand Central of the West,” the Salesforce Transit Center opened in August near the heart of downtown after nearly a decade of construction. It was expected to accommodate 100,000 passengers each weekday, and up to 45 million people a year.

The center is operated by the Transbay Joints Power Authority and its executive director Mark Zabaneh said workers discovered the crack around 10 a.m. while replacing roofing tiles. Zabaneh said engineers spent the day inspecting the damage and decided to shut the station around 5 p.m., just as the afternoon rush hour started.

“The beam is cracked,” Zabaneh said. “The behavior of the beam is unpredictable.”

Zabaneh said the crack was found near a weld on a stress-bearing horizontal beam. He said he did not know how long the crack was, but he told reporters that American steel was used in the center’s construction.

Zabaneh said the cause and the extent of the damage were unknown and the decision to close the terminal was made out of an “abundance of caution.”

He said structural engineers would be working at the building Tuesday night to assess whether it is safe for people to return.

Buses were rerouted to a temporary transit center about two blocks away that was used during the center’s construction. A downtown street that runs under the beam was also ordered closed indefinitely, causing traffic chaos at the same time some streets were closed for a conference sponsored by Salesforce that was expected to draw 170,000 attendees.

Enveloped in wavy white sheets of metal veil, the five-level center includes a bus deck, a towering sky-lit central entrance hall and a rooftop park with an outdoor amphitheater.

The San Francisco Chronicle reported that the complex faced delays in putting out contracts to bid, and the winning bids were ultimately higher than expected. The terminal’s cost rose from $1.6 billion at its 2010 groundbreaking to more than $2 billion in 2016 because of what one analyst called “optimistic assumptions,” according to the Chronicle.

The project, a commanding presence in the city’s South of Market neighborhood, is financed by land sales, federal stimulus grants, district fees and taxes, bridge tolls, and federal and state funds.

It sits adjacent to another dubious landmark, the so-called sinking condominium, Millennium Tower, which has settled about 18 inches (45 centimeters) since it opened over a former landfill in 2009. Homeowners have filed multiple lawsuits against the developer and the city, some alleging that construction of the transit center caused the Millennium Tower’s sinking.

Zabaneh said he did not believe that the cracked beam was related to ongoing problems at Millennium Tower.

The online business software company Salesforce, which opened its adjacent 61-story Salesforce Tower three months ago, bought naming rights to the center in 2017 as part of a 25-year, $110 million sponsorship agreement.

TribLIVE commenting policy

You are solely responsible for your comments and by using TribLive.com you agree to our Terms of Service.

We moderate comments. Our goal is to provide substantive commentary for a general readership. By screening submissions, we provide a space where readers can share intelligent and informed commentary that enhances the quality of our news and information.

While most comments will be posted if they are on-topic and not abusive, moderating decisions are subjective. We will make them as carefully and consistently as we can. Because of the volume of reader comments, we cannot review individual moderation decisions with readers.

We value thoughtful comments representing a range of views that make their point quickly and politely. We make an effort to protect discussions from repeated comments either by the same reader or different readers

We follow the same standards for taste as the daily newspaper. A few things we won't tolerate: personal attacks, obscenity, vulgarity, profanity (including expletives and letters followed by dashes), commercial promotion, impersonations, incoherence, proselytizing and SHOUTING. Don't include URLs to Web sites.

We do not edit comments. They are either approved or deleted. We reserve the right to edit a comment that is quoted or excerpted in an article. In this case, we may fix spelling and punctuation.

We welcome strong opinions and criticism of our work, but we don't want comments to become bogged down with discussions of our policies and we will moderate accordingly.

We appreciate it when readers and people quoted in articles or blog posts point out errors of fact or emphasis and will investigate all assertions. But these suggestions should be sent via e-mail. To avoid distracting other readers, we won't publish comments that suggest a correction. Instead, corrections will be made in a blog post or in an article.